WETROOM INSTALLATION PROCEDURE
|
|
|
S T A G E 1
Prepare Floor area and
Run drainage to suit.. Run Hot and Cold Services for
Shower. |
S T A G E 2
Frame, Strengthen and
Play-line below Tray, and the rest of the floor area
in the Bathroom |
|
|
S T A G E 3
Fix Aquadeck wetroom Tray
into position and adjust Gully.. |
S T A G E 4
Bond & Tank (waterproof)
whole floor area Using Aquadeck Tilesafe tanking
membrane & kit. Internal & External Corners first. |
|
|
S T A G E 5
Continue to Tank
(waterproof) whole floor space Using Aquadeck
Tilesafe tanking membrane & kit.. |
S T A G E 6
Tile Over Membrane using
Specific Make of Tile Adhesive for Wet-floors.
Mosaic Tiling above the Tray.. |
|
|